Smart Solutions case studies highlight how MCAA contractors and Manufacturer/Supplier Council members collaborate to improve productivity, manage costs, and solve real‑world project challenges. Each case study focuses on practical applications of products, technologies, and processes that deliver measurable results across mechanical construction, service, fabrication, and operations.

Through real project examples, Smart Solutions provides insight into how contractors are applying innovative solutions to streamline workflows, improve coordination, and enhance overall performance. Explore the case studies below to identify ideas, approaches, and proven practices that can be adapted to your own operations.

Filters

Category

Manufacturer/ Supplier

Contractor

Conti Corporation Cuts Installation Time with Erickson Incorporated Aerial Lift and Placement

Innovative aerial service provider Erickson Incorporated successfully conducted 13 chiller equipment lifts to the top of the JPM Chase building in Belleville, MI, in just two-and-a-half hours, allowing Conti Corporation to cut installation time dramatically. Erickson’s placement lifts saved time on the ground and also saved labor costs, because they were much more efficient than standard ground-based methods.